A custom home at this level takes two to three years, counted from the first conversation to the day you move in. Design and engineering usually run six to twelve months. Construction runs eighteen to thirty months. Approvals sit between the two, and they are the part nobody can fully predict.
If you’ve been wondering how long it takes to build a custom home, that is the short answer. The longer answer depends on where you build. We work on the Orange County coast and in the mountains around Park City, and the same house would follow a different calendar in each place. Here is where the time actually goes, and what moves it.
Key Takeaways
Plan on two to three years from first conversation to move-in for a fully custom home.
Design and engineering take six to twelve months. Construction takes eighteen to thirty months.
Permitting is the biggest variable. On the coast, that means city review and, on some sites, the California Coastal Commission. Around Park City, it means county review and often a community architectural review committee.
Park City has a short building season, so the start date matters. Miss the window and the schedule can slide by months.
The builds that stay on schedule are the ones with complete drawings, decisions made on time, and a builder involved from the beginning.
The Custom Home Building Process, Step by Step
How long it takes to build a custom home comes down to five stages. These are the steps to build a custom home with us, whether the lot sits above the sand or on the side of a mountain.
1. The First Conversation
This is the shortest step. You talk with Brad or Josh, not a salesperson. We look at the site, listen to what you want the house to do, and decide together whether we are the right builder for it. You can read more about the two of them on our Heritage page.
2. Design, Engineering, and Budget (6 to 12 Months)
Bring your architect or work with one we trust. Either way, we are in the room early. While the drawings develop, the structural, civil, and soils engineering happens alongside them, and we price the house line by line from actual subcontractor numbers.
This stage feels slow because nothing is being built yet. It is also where the schedule is won or lost. A complete set of drawings and a full list of selections means fewer questions once the crews arrive.
3. Approvals and Schedule (Varies by Site)
We handle permitting in both states. How long it takes depends on the jurisdiction, the community, and the lot itself. Some sites clear review in a few months. Others take much longer, and we will tell you which kind yours is before you commit. You get a full construction schedule before we break ground.
4. Construction (18 to 30 Months)
Site work and foundations come first, then framing, which goes up faster than most people expect. After that comes a long, quiet stretch. Mechanical, electrical, plumbing, shading, and sound control all go into the walls while they are still open. From the street, it can look like nothing is happening. It is some of the most important work in the house.
Finishes come last and take patience. Stone, millwork, glass, and metal at this level are made to order and set by hand. A superintendent is on site every working day, and you get an update every week.
5. Punch List and Move-In
We walk the house with you, room by room, until every item is closed. Then you move in, and the same team stays on to look after the home.
Building a Custom Home in Park City
In the mountains, the calendar is set by the weather as much as by the drawings. Our first Utah homes are underway near Park City and Deer Valley, and three things shape the timeline there.
The building season is short. Excavation and foundations are best done in the warm months. If approvals land late, the start can wait for the ground to thaw, and that delay carries through the rest of the job.
The site work is heavier. Steep lots need excavation and retaining before anything else. Footings go below the frost line, and the structure is sized for deep snow. All of it adds time at the front of the build.
There can be two rounds of review. Summit County and Wasatch County each run their own process. Many lots in communities like Promontory and Deer Valley also need approval from an architectural review committee before the county will look at the plans.
The custom home building process is the same one we use in California. The sequencing is what changes. We plan the schedule so the house is closed in before winter and the interior work can carry on through the snow. See how we approach building in Utah.
Building a Custom Home in Orange County
On the coast, the weather is rarely the problem. The approvals and the site are.
Coastal review comes first. Nearly every lot we build on is in the coastal zone, so the city reviews the project before a building permit is issued. On some sites, the California Coastal Commission reviews it next, which can add six months or more.
Bluff lots start below ground. A home on a bluff needs caissons and shoring before the house itself can begin. That work is slow, exacting, and invisible when the home is done.
Beach streets are tight. Narrow roads limit where materials can be staged and when a crane can reach the site. Deliveries have to be planned to the day.
Salt air narrows the material list. Only certain metals and glazing hold up near the ocean, and the right ones are often made to order.
Inland parcels, like those around San Juan Capistrano, generally move through approvals faster than sites in Dana Point, Laguna Beach, or Corona del Mar. You can see finished homes from this stretch of coast in our portfolio, and read more about building in Southern California.
What Keeps a Build on Schedule
Some of the timeline is out of anyone's hands. A review board meets when it meets. Snow arrives when it arrives. Most of the rest can be managed, and it usually comes down to a few habits.
Bring the builder in during design. Problems are cheaper and quicker to solve on paper than in concrete.
Finish the drawings before breaking ground. Starting with open questions feels faster. It almost never is.
Make selections on a schedule. We give you a calendar of decisions so that stone, fixtures, and glass are ordered well ahead of the day they are needed.
Hold the design once framing starts. Changes after that point ripple through every trade that follows.
Expect one surprise. Every site has one. What matters is hearing about it early, with options and a number attached.
FAQs
How long does it take to build a custom home from start to finish?
Plan on two to three years from the first conversation to move-in. That includes six to twelve months of design and engineering, the approval period, and eighteen to thirty months of construction.
How long does construction take on its own?
Eighteen to thirty months for a home at this level. Size, site conditions, and the complexity of the finishes account for most of the range.
Is it faster to build in Park City or Orange County?
Neither is reliably faster. Coastal lots tend to spend more time in approvals. Mountain lots tend to spend more time on site work and are tied to the building season. The total often lands in the same two to three year range.
Can you build through the winter in Park City?
Yes, once the house is enclosed. Interior work continues through the cold months. The work that depends on the weather is at the start, which is why the timing of approvals and groundbreaking matters so much in the mountains.
What causes the longest delays?
Permitting and late decisions. Review timelines are set by the city, county, or community. Decisions are set by you and your design team, and keeping them on schedule is the most direct way to protect the move-in date.
When should I contact a builder?
As early as you can, ideally before the design is far along or even before you buy the lot. An early conversation costs nothing and often saves months.
Final Thoughts
So how long does it take to build a custom home? Two to three years, if it is done properly. That is a long time to wait. It is also a small part of the decades you will spend living there, and the time is what allows the house to be built once and built right.
We take on a handful of homes a year, and every one gets a schedule before the first shovel goes in. If you are thinking about building in Park City or on the Orange County coast, tell us about the site and what you have in mind. Start your build.